11915 GARR AVE encroachment permit for buried Lumos Fiber
Lumos Fiber is lining up to bury new fiber in the city right-of-way along Garr Ave at 11915 Garr Ave, starting at the Evergreen Rd intersection; the plan calls for directional boring to place two 1.25" HDPE conduits and to pull and splice about 2,302 feet of fiber. The parcel is owned by Klarer Peter K & Denise, work is scheduled Feb. 9–27, 2026 with requested hours of 8 AM–5 PM and likely lane and sidewalk closures, with Danielle Allen listed as project engineer and Ledcor as the general contractor.