Two dirt cuts and a lane closure are planned at 7433 Ralston Ave
Give 7433 Ralston Ave a little room. Two dirt cuts, each about 3 by 5 feet, are on the way there, and lane closure is part of the plan.
The city signed off on the work, which is set to run from March 1, 2027 through March 1, 2028. Louisville Gas and Electric is the name on it, so expect that stretch to get a little less friendly to your commute.
The city signed off on the work, which is set to run from March 1, 2027 through March 1, 2028. Louisville Gas and Electric is the name on it, so expect that stretch to get a little less friendly to your commute.
Source: Accela Public Works