1430 Christy Ave Continuation Permit for Lead Replacement Project
Louisville Water Company is doing a lead replacement at 1430 Christy Ave for owner Steven A. Roosa under a continuation permit. Expect one 4' x 5' pavement cut on the east side (between Edward St. and Rubel Ave), lane and sidewalk closures with the road plated and reopened at the end of shifts, restoration per LMPW policy, work scheduled May 13–30, 2026; project manager Joseph Sloan and contractor Basham Construction are listed as contacts and residents were notified on 5/12/2026.
Source: Accela Public Works