3001 Chamberlain Ln encroachment permit issued for fiber optic placement
Team Fishel, on behalf of Crown Castle, will be installing roughly 1,064 feet of new 2-inch HDPE duct with fiber and one handhole via directional bore near 3001 Chamberlain Ln on property owned by Ford Motor Co World Headquarters. The work includes excavation, a few small pavement cuts, and a temporary shoulder closure along the north side of Chamberlain Ln (southeast of Westport Rd), with lane closures planned. Expect the crew onsite from July 20 to August 2, 2026.
The city has not published a date for when this began.
Source: Accela Public Works