101 W CHESTNUT ST Encroachment Permit issued for water vault repairs
Louisville Water (applicant Brad Walter McBride) will be repairing six water vaults and making one 5x5 sidewalk cut at 101 W Chestnut St — all affected sidewalk will be replaced within 48 hours and restored per LMPW utility policy. The excavation work (with temporary sidewalk closure and traffic control adjusted as the job progresses) is scheduled roughly 05/04/2026–06/05/2026; the property owner is RMHCK Real Estate LLC and project manager Clay Robinson (502-919-2861) is listed for questions, and the site has individual landmark status requiring UD written approval.
Source: Accela Public Works