9801 Lower River Rd Encroachment Permit for Fiber Optic Placement
Team Fishel, working on behalf of Crown Castle, plans to install fiber at 9801 Lower River Rd by placing about 750 feet of new 2-inch HDPE duct (with plans showing a total of roughly 1,440 feet) and two 24Γ36Γ24-inch handholes. The property is owned by 6253 LLC, and all work is directional bore outside the pavement in the shoulder/sidewalk area. Expect temporary lane, shoulder, and sidewalk closures between Sun Valley Dr and Johnsontown Rd from April 27 to May 10, 2026, with no full road closures noted.
Source: Accela Public Works