7201 JOHNSONTOWN RD applied for encroachment permit for fiber optic placement
Team Fishel, on behalf of Crown Castle, is planning a fiber‑optic installation along Johnsontown Road with work around 7201 Johnsontown Rd scheduled for March 23–April 5, 2026. The crew will directional‑bore roughly 1,676 feet of new 2‑inch HDPE duct with fiber and install three 24"x36"x24" handholes outside the pavement in the shoulder/sidewalk area, so expect temporary shoulder and sidewalk closures; the property owner is Jefferson County School District Fin and a restoration plan is on file.
Source: Accela Public Works