233 W BROADWAY Encroachment permit for LGE curb lane/sidewalk closures
Louisville Gas and Electric is scheduled to work at 233 W Broadway for St Francis School Inc., replacing an electric vault, installing underground cable, and putting a transformer into the vault. Expect lane closures of the westbound and eastbound curb lanes (not at the same time) plus the northernmost sidewalk closed; the job runs from December 9, 2025 to January 6, 2026, previous cuts have been restored, and Kaitlyn Downs and project engineer Chris Spalding are the listed contacts.